Bad news for Forge Group shareholders

GREG ROBERTS
Last updated 10:26 15/01/2014

Relevant offers

World

Strippers 'part of doing business' Argentina's last-ditch effort to avoid default Scare trims McDonald's Hong Kong menu Skyscraper mania grips China The jobless existence of Spain's graduates Crocs cuts jobs but 'isn't in crisis' Aussie dollar bounces on inflation figures Will Rupert Murdoch become media king? One in 25 New Yorkers a millionaire - study Billionaire calls for three-day working week

Forge Group's shareholders have been punished after the company announced another profit writedown, bringing the total in less than two months to up to A$155 million ($124 million).

The latest problems for the Perth engineering group relate to a A$23m to A$28m cost blow-out at the West Angelas Power Station Forge is building for Rio Tinto in Western Australia's Pilbara.

The total profit hits associated with that project and its DPS station in Mt Isa, Queensland, to A$150-155m following a A$127m writedown in late November.

On Tuesday morning, Forge's shares came out of a two-day trading halt and plunged 30 per cent.

It clawed back to close 22.5 cents, or 18 cents, down at A$1.025, representing a A$19m-plus fall in market capitalisation to below A$90 million.

The shares were A$6.90 10 months ago.

Forge shares plummeted 84 per cent, losing A$300m in its market value, in one day in late November when it came out of a three-week trading halt to announce gas station writedowns and forecast an annual loss of up to A$90m.

Forge chief executive David Simpson said, in a teleconference, that Rio Tinto, the bank and Forge's other financiers continued to back the company and that the extra net costs of up to A$19m announced on Tuesday would come out of existing funds.

ANZ Bank stepped in as creditors late last year with more generous debt facilities to rescue Forge from a cashflow crisis and possibly administration when it had to find A$45m to complete the gas power station contracts.

However, the deal gave ANZ warrant options over 13 per cent of Forge's shares which, if exercised, would dilute other shareholdings.

Simpson said the company had only uncovered the extra engineering and other needed work last week, and that it would delay the West Angelas project by three months.

The plant is due to be completed by August this year.

"The market announcement comes to us today regrettably,' he said.

OptionsXpress market analyst Ben Le Brun said he thought Forge might still need a capital raising, which some thought could be avoided through its new debt deal.

"The downgrade of the power stations was unfortunate as the new power division was expected to insulate the company somewhat in light of the broader mining slowdown," he said.

The company had some good news, however, announcing that it had secured bonding facilities from financiers backing its recently won A$1.5 billion contract with Gina Rinehart's Roy Hill iron ore project.

Ad Feedback

- AAP

Special offers

Featured Promotions

Sponsored Content