Arts Centre restoration under way

CHARLIE GATES
Last updated 13:45 04/02/2013
arts centre landscape
Dean Kozanic

REPAIRS: New bracing is installed on the Art's Centre clock tower today.

Relevant offers

Christchurch earthquake

Study into 'lateral spreading' earthquake cracks launched Insurance Council asks Kaikoura District Council to pull video from its Facebook page Tower Insurance chairman Michael Stiassny expresses frustration at claims holdouts 'Quake brain' blamed for Cantabrians' weak memories and poor direction - study Red Cross pays out $98 million in cash grants since Canterbury earthquakes Major artwork gifted as a legacy for Christchurch quake victim Clip art: A visual Christchurch earthquake story New plans submitted for red-zone water facility Manslaughter charges the only option in CTV building earthquake case Canterbury earthquake memorial 'a place to grieve and hope' - English

The $36 million restoration of the Great Hall and the Clock Tower at the Christchurch Arts Centre has taken a step forward with the arrival of steel braces.

The braces were craned in today to stabilise the areas at the base of the Clock Tower that used to house Rutherford's Den and Le Cafe.

The braces mean restoration work can start at ground level.

The project to restore the northwestern corner of the historic Arts Centre complex is due for completion in 2015.

The Registry building on the northeastern corner of the centre is due to open as commercial office space in July, but a tenant has not yet been found.

Repair and strengthening work at the centre is expected to take seven years and cost $290m.

The centre will reopen in phases as parts of the complex are restored.