Arts Centre restoration under way

CHARLIE GATES
Last updated 13:45 04/02/2013
arts centre landscape
Dean Kozanic

REPAIRS: New bracing is installed on the Art's Centre clock tower today.

Relevant offers

Christchurch earthquake

Recovery team recognise the good Samaritans of Kaikoura who helped after the earthquake Police decide against charges over Southern Ink and Riccarton Rd earthquake deaths Man to create near-perfect replica of Christchurch heritage house Steve Hansen pays tribute to the late Sir Ron Scott Family support memorial for nurses lost in Christchurch earthquake Shortland Street quake show should have carried a warning, say traumatised viewers Christchurch quake rescuer Bill Toomey wins fight for ACC cover for post-traumatic stress Study into 'lateral spreading' earthquake cracks launched Insurance Council asks Kaikoura District Council to pull video from its Facebook page Tower Insurance chairman Michael Stiassny expresses frustration at claims holdouts

The $36 million restoration of the Great Hall and the Clock Tower at the Christchurch Arts Centre has taken a step forward with the arrival of steel braces.

The braces were craned in today to stabilise the areas at the base of the Clock Tower that used to house Rutherford's Den and Le Cafe.

The braces mean restoration work can start at ground level.

The project to restore the northwestern corner of the historic Arts Centre complex is due for completion in 2015.

The Registry building on the northeastern corner of the centre is due to open as commercial office space in July, but a tenant has not yet been found.

Repair and strengthening work at the centre is expected to take seven years and cost $290m.

The centre will reopen in phases as parts of the complex are restored.