Four schools for $200m by 2018

Last updated 17:03 28/07/2014

Relevant offers


Ministry of Education blamed for almost certain closure of childcare centre Ministry of Education is shelling out for more classes in Waikato Southland teacher creates board games to teach kids manners and safety messages Staff cuts proposed in Victoria University's School of Languages and Cultures Cool Aeronautics comes to Pinehaven South Auckland kids get passionate about violin despite limited resources New blocks and redevelopments: $17m for two Waikato schools Nuclear physics paper written by iOS autocomplete Wellington student Finn Lewis wins TV gameshow Spellbound Students past and present celebrate 150 years of Grovetown School

The Education Ministry is down to two private contenders in the race to build four schools for $200 million before 2018.

The tender process for building Aranui Community School and Rolleston Secondary School in Canterbury, Queenstown's Wakatipu High School, and a yet-to-be-announced Auckland school is down to companies Investec and Future Schools.

The Canterbury and Auckland schools are scheduled to open in January 2017, followed by Wakatipu High in January 2018.

Ministry head of infrastructure Kim Shannon said the four schools were to be built using a public-private partnership procurement model. The building design, construction and financing would be the responsibility of a private team of sponsors, builders, architects, and facilities managers.

The contract for the successful tender would include property maintenance for 25 years, "leaving school leaders to focus on raising student achievement".

In other state schools, the school itself was responsible for property maintenance.

"Based on national and international experience and lessons learnt from the ministry's first PPP at Hobsonville Pt primary and secondary schools, we expect the second partnership has an estimated cost savings of between 2 per cent to 8 per cent over the 25-year period," Shannon said.

The ministry estimated the cost of construction and maintenance for the project to be more than $200m, paid to the private partner quarterly, with this payment reduced if the school facilities did not meet the standards specified in the contract.

She was "delighted" with the high quality of tenderers, who would proceed to the next stage.

Investec is sponsored by Investec, with construction by Naylor Love Construction, Opus Architecture as the lead designer, and facilities management provided by Spotless Facilities.

Future Schools is sponsored by Morrisons, with construction by Hawkins Group, ASC Architects as the lead designer, and facilities management provided by Programmed Facility Management.

Final bids would be submitted in October.