AFT Pharmaceuticals to list on NZX and ASX in December Intel employee paid friend to call in bomb threat so he didn’t have to go to work Xero founder Rod Drury cashes in $20m of Xero shares iPredict to close after Govt refuses anti-money laundering law exemption Revealed: The highest paid public servants Seven days of sevens rugby festival for Wellington rugby series Lecturer claiming cyber-bullying takes objection to ERA investigator Mitre 10 ends Mr Mega without even a goodbye - Vaoga Million-dollar tax fraud lands Taranaki couple behind bars GE becomes Latitude Financial Services after acquisition

About 200 staff at Mainzeal Property and Construction were made redundant today as the company’s receivers continued a review of operations.

Receiver Colin McCloy of PricewaterhouseCoopers said about half of the company’s approximately 400 staff had been made redundant.

They were a mix a staff from its Auckland head office and various building sites around the country.

McCloy said it was necessary to review the company’s staffing levels in order to urgently reduce cash flows.

The receivers were also conducting a site by site review of all of the company’s projects to work out the best strategy for each of them.

This involved about 40 projects and McCloy said they had reviewed about half of them since being appointed last Wednesday.

Since Friday the receivers had also been working with contractors and sub-contractors to give them access to the sites, to ensure all parties involved were safe and that property that rightfully belonged to contractors could be retrieved in a controlled manner, McCloy said.

The receivers are also in talks with several parties that are interested in buying the business and assets of Mainzeal, either in parts or as a whole, he said.