London Olympic Park gets $468m makeover

KEITH WEIR
Last updated 09:40 28/11/2012
Olympic Park
Getty Images
RENOVATIONS: The Olympic Park needs a complete makeover before it is suitable to host other events and for public use.

Relevant offers

Other Sports

Transgender issue hits the mat with Texas wrestler's win Deontay Wilder: I'll fight Joseph Parker anywhere Dean Barker questions Team New Zealand's late arrival in Bermuda for America's Cup Boxers Manny Pacquiao, Amir Khan agree to 'super fight' in April Olympic champion Mo Farah denies doping after coach named in report Five medals for Kiwi track cyclists at Los Angeles World Cup Eliza McCartney soars over Oceania record 4.82m to light up Auckland Track Challenge Ryan Crouser monsters Tom Walsh again, then predicts dual world record assault Deontay Wilder retains WBC heavyweight title and quickly calls out Joseph Parker Southland touch players Trisha Hopcroft, Kate Day and Ben McKerchar earn NZ Touch Blacks selection

London's Olympic Park has taken on the air of a construction site again, with work under way on a 292 million pound transformation before Britons can use facilities like the swimming pool and cycle trails.

Builders in hard hats were today dismantling temporary seats towering above the pool where American Michael Phelps won a record 18th Olympic gold in August.

However, the failure to settle on a tenant for the centrepiece Olympic Stadium, built at a cost of some 430 million pounds, has taken some of the gloss off a successful Games that silenced the sceptics.

Premier League club West Ham United remain the most likely tenant but wrangling over the division of the costs of turning the stadium into one also suited for top-flight soccer has slowed the process.

The London Legacy Development Corporation (LLDC), the public body responsible for the site, is scheduled to discuss the stadium issue again next week and there are hopes that a decision will be announced before the end of the year.

However, the LLDC has warned the stadium will not open before 2015, prompting a frustrated UK Athletics Chairman Ed Warner to denounce the delay as a farce.

The Olympic Stadium will hold the 2017 World Athletics Championships and is on the list of potential venues to host matches during the 2015 rugby World Cup but that deadline is beginning to look tight.

MAJOR EVENTS TARGETED

The Games cost the British public around 9 billion pounds and spending during the Olympics helped to give a one-off boost to Britain's struggling economy.

London has restarted free bus tours around the Olympic Park, keen to maintain the goodwill generated by the Games and show that it will have a viable future as part of plans to regenerate what was long a rundown part of east London.

Workers on the site on a bleak November day were focused on getting it ready to reopen to the public next July - a year on from the Games - with a new name of the Queen Elizabeth Olympic Park.

"We want the park to open as quickly and as safely as possible," Colin Naish, director of infrastructure at the LLDC told reporters, adding the target was for a phased reopening to be completed by the middle of 2014.

Contractors Balfour Beatty and BAM Nuttall are expected to employ up 1000 workers on the conversion.

The swimming pool is scheduled to be used as a public leisure centre from 2014, although London has also bid to stage the European swimming championships at the venue in 2016.

Ad Feedback

Britain is seeking to build on the good publicity generated by the Olympics to attract lucrative international events.

It has also applied to stage the 2016 world track cycling championships on the London site.

- Reuters

Special offers
Opinion poll

Will Shane Cameron beat Kali Meehan on Saturday?

For sure. Cameron will knock him out.

It will be close but I think Cameron on points.

Meehan will knock him out. This is his last fight.

I'm tipping Meehan to win on points.

Vote Result

Featured Promotions

Sponsored Content