Backlog of defective buildings and shoddy workmanship sparks calls for building warranties 'Overkill' central Christchurch intersection has 19 lights Home owners aghast at fee for Southern Response class action Court of Appeal seeks to rein in 'shemozzle' arising from CTV building case Christchurch Dilemmas: Taking power back in Christchurch Steel mesh in some homes could be non-compliant Housing provider set to use shipping containers for emergency housing A new job and a new town for the Johnson family after Canterbury's earthquakes Christchurch Dilemmas: Christchurch's mental health crisis Nationwide building boom creating next leaky buildings crisis

An earthquake-damaged footbridge spanning the Avon River has been dismantled after nearly two years of being off-limits.

Stronger Christchurch Infrastructure Rebuild Team (Scirt) project co-ordinator Colin Hey said the Snell Pl bridge in Dallington was badly hit in the February 2011 quake.

"The back of the bridge was broken. It was effectively squashed between the two banks as they moved inward," he said.

"It's an arched bridge and the centre of it was pushed up in the air."

The 46-year-old bridge was cut through at the centre split, Hey said, and cranes removed the two parts.

It is the second Avon footbridge in eastern Christchurch to go since the quakes, after the Porritt Park bridge was taken apart in November, and will soon be joined by a third.

The warped and twisted Medway St footbridge - a symbol of the earthquakes' destruction since September 2010 - will be removed on February 12, after a community farewell.

Burwood-Pegasus community board chairwoman Linda Stewart said the Richmond bridge was a "community connection" and its loss was sorely felt.

"We're all very precious about that bridge and all the footbridges. If I have my way, we'll have more footbridges, not less."

She will meet the Dallington Residents' Association next week to plan the event, which might include a barbecue and a reading.

Council infrastructure team leader Will Doughty said the bridges would be replaced, but community consultation was needed to decide whether any location changes were appropriate.

Scirt is also managing the repairs of the historic Antigua St footbridge beside Christchurch Hospital.

The repair plan was still being devised, a spokeswoman said, and work would not start until March or April.

Ad Feedback

- The Press


Special offers
Opinion poll

Which memorial design do you like most?

Memorial Wall with a reflective pond

Table and Chairs

A Green and Peaceful Landscape

Call and Response

Riverside Promenade

A Curved and Inclusive Memorial Wall

Vote Result

Related story: Christchurch earthquake memorial designs unveiled

Featured Promotions

Sponsored Content